M-35 rebuild underway in Marquette

MARQUETTE – Work on the MDOT rebuilding project from east of Smith Street to the east branch of the Escanaba River in Gwinn resumed today, weather permitting.

MDOT, Forsyth Township, and the Marquette County Road Commission are investing about $4.4 million to rebuild 0.7 miles of M-35 in Gwinn.

Work includes asphalt rebuilding; concrete curb, gutter, and sidewalk ramp installation; storm sewer and drainage repairs; bridge approach repairs; water main and sanitary sewer repairs; detour route improvements; and pavement markings. Work began last year, with about two blocks of the project remain to be completed.

During the project, one lane of alternating traffic will be maintained from North Billings Street to east of Smith Street using temporary signals.

Based on economic modeling, this investment is expected to support 53 jobs.

 

The project is expected to be completed in June.

Leave a Comment

###

UpNorthVoice.com is Northern Michigan's source for community news.

We cover seven counties including Crawford, Roscommon, Oscoda, Ogemaw, Iosco, Arenac and Montmorency counties in print and / or online.

We are also a full-service commercial design and printing house. Our specialty is custom commercial printing, as well as the creation of clothing, cups and other marketing products.

To submit information for publication, or for questions regarding promotion of your business through web or print, as well as promotional items such as hats or cups, please email info@UpNorthVoice.com, or call 989-275-1170.

Advertisement